Daily Archives: November 1, 2017


Fire Hall Update

Good afternoon Tuscany! We wanted to get you some updated information on the construction progress of our new fire hall! Please note the following dates for upcoming projects with traffic implications. November 6th there will be a crane onsite moving large deliveries of mechanical. There will be a notable increase in traffic making these deliveries on the day. November 14th there will be a large concrete pour for the apparatus bay slab. This will create a noticeable increase in traffic for the day. Also a general summary of the progress thus far. -Masonry will be ongoing through October, with an increased focus on exterior brickwork. There will be some increased heavy traffic on the site, via Tuscany Way NW, due to block and brick deliveries. -Glazing will be ongoing through October, with an increased focus on curtainwall. -External site concrete and asphalt paving will be completed over the coming weeks. […]