Daily Archives: May 2, 2018


Twelve Mile Coulee Road Upgrades: Construction Update

Twelve Mile Coulee Road Upgrades: Construction Update April 30, 2018 to May 30, 2018 Tusslewood Drive to Tuscany Way Construction Activities: Construction of South Bound Lanes o Grading and construction of retaining walls o Street Lighting o Paving and Concrete Surfacing Traffic Impact: Generally there will be no impact to traffic flow Periodic short stoppages may be required for construction access Reduced lane widths will be required Estimated Duration: Road Construction in this area is anticipated to be completed June 30th with Landscaping continuing into July. Tuscany Way to North of Watermark Villas Construction Activities: Sidewalks, streetlighting and landscaping Traffic Impact: Generally there will be minimal impact to traffic as two-way traffic will be maintained on narrowed lanes. Estimated Duration: Road Construction in this area is anticipated to be completed June 30th with Landscaping continuing into the fall in conjunction with the work down to 80th. 80th Ave NW to […]